Mine shaker test method

After completion of mine shaker installation, you need to load running tests on local installation unreasonable adjustments to protect the quality of the equipment.

1, without the mine shaker test 8h failure Feeding equipment before installation project acceptance.

2, mine shaker commissioning time shall not be less than 8h. During this time, a smooth start quickly observe whether a sieve, vibration and operation stability, no special

noise amplitude observed by amplitude license compliance.

3, mine car shaker within 4h, bearing stone feeding machine temperature is rising, and then remain stable. The maximum temperature does not exceed 75 ℃, the temperature rise should not exceed 40 ℃.

4, mine shaker commissioning time shall not be less than 8h. During this time, a smooth start quickly observe whether a sieve, vibration and operation stability, no special

noise amplitude observed by amplitude license compliance.

5, mine shaker 2-4h after driving down to check if the connecting parts are loose, if loose, to be fastened before driving. If the mine after a sharp increase in car shaker

abnormal noise or bearing temperature, should immediately stop and check whether the rotating shaft is flexible and well lubricated, etc.

Subject to troubleshooting and then start.

6, when the mining operation with a vibrating screen, vibrating screen box should not produce yaw. If there yaw, the reason may be on both sides of the spring height is too

large, hanging rope pull uneven rotation axis is not horizontal or triangular tape too tight and should be adjusted accordingly.