Circular Vibrating Screen Installation Precautions




Circular Vibrating Screen Before installing, first by mechanical packing slips, checks are complete and damaged parts, including vibrators Date from the factory, if more than

six months, must be re-washable and assembly, and replace it with clean oil .
    Installed by the time, in strict accordance with the setup diagram supplied mechanical equipment installation, including supporting the chassis must be mounted horizontally,

based on the foundation should have sufficient stiffness and strength to support the entire shaker dynamic load and static load.
    Screen box corners have a lug, bearing chassis corners have lifting holes, as required for lifting, not directly linked to the vibrator on lifting the entire sieve, sieve

box and ensure hopper, chute (chute) such a class Feeding equipment of non-sports parts should be maintained between the minimum clearance of 75mm.
    Strict requirements to install, make sure the spring seat and screen box friction damper plate on a 10mm gap between. Damping spring free height by matching, respectively,

so that the left and right sides of the front end or back-end spring free height equal as far as possible, the error does not exceed 5mm. Screen box after installation, around

the screen surface protection

Support level, or, in the spring seat Screening machine member and the support pad Q thin sheet iron.